幻灯片注释Lect03



《幻灯片注释Lect03》由会员分享,可在线阅读,更多相关《幻灯片注释Lect03(86页珍藏版)》请在装配图网上搜索。
1、,,,,,,,Click to edit Master title style,,Click to edit Master text styles,,Second level,,Third level,,Fourth level,,Fifth level,,Software Project Management,*,Software Project Management,,Lecture,3,,Size and Cost Estimation,Software Project Management,,Overview,,Different level of estimation,,Projec
2、t Evaluation,,Introduction to Estimation,,Size Estimation,,Cost Estimation,Software Project Management,2,,Different level of estimation,,Before a project is decided to pursue,继续,,The estimation is coarse,,The estimation is in high level terms,,Profit? Good to the,organization,? etc.,,After the proje
3、ct is decided to go ahead,,More detailed size and cost estimations are required,Software Project Management,3,,Project Evaluation,,It is a high level assessment of the project,,to see whether the project is worthwhile to proceed,,to see whether the project will fit in the strategic planning of the w
4、hole organization,Software Project Management,4,,Project Evaluation - Why,,Want to decide whether a project can proceed before it is too late,,Want to decide which of the several alternative projects has a better success rate, a higher turnover,周转,, a higher ...,,Is it desirable to carry out the dev
5、elopment and operation of the software system,Software Project Management,5,,Project Evaluation - Who,,Senior management,,Project manager/coordinator,,Team leader,,Software Project Management,6,,Project Evaluation - When,,Usually at the beginning of the project,,e.g. Step 0 of Step Wise Framework,So
6、ftware Project Management,7,,Project Evaluation - What,,Strategic assessment,,Technical assessment,,Economical assessment,,Software Project Management,8,,Project Evaluation - How,,Cost-benefit analysis,,Cash flow forecasting,,Cost-benefit evaluation techniques,,Risk Analysis,,Software Project Manage
7、ment,9,,Strategic Assessment,,Use to assess whether a project fits in the,long-term goal,of the organization,,Usually carry out by senior management,,Need a strategic plan that clearly defines the objectives of the organization,,Evaluate individual projects against the strategic plan or the overall
8、business objectives,Software Project Management,10,,Strategic Assessment (,c,ont’d,),Programme management,,suitable for projects developed for use in the organizations,,Portfolio,卷宗,,management,,suitable for project developed for other companies by software houses,Software Project Management,11,,SA
9、– Programme Management,,Individual projects as components of a programme within the organization,,Programme as “a group of projects that are managed in a coordinated way to gain benefits that would not be possible were the projects to be managed independently”,,by D.C. Ferns,,Journal of Project Mana
10、gement,,Aug. 1991,Software Project Management,12,,SA – Programme Management Issues,,Objectives,,How does the project contribute to the,long-term goal,of the organization?,,Will the product increase the market share? By how much?,Software Project Management,13,,SA –,Programme,Management Issues (cont’
11、d),IS plan,,Does the product fit into the overall IS plan?,,How does the product relate to other existing systems?,Software Project Management,14,,SA – Programme Management Issues (,c,ont’d,),Organization structure,,How does the product affect the existing organizational structure? the existing work
12、flow? the overall business model?,Software Project Management,15,,SA – Programme Management Issues (,c,ont’d,),MIS,,What information does the product provide?,,To whom is the information provided?,,How does the product relate to other existing,MISs,?,Software Project Management,16,,SA – Programme Ma
13、nagement Issues (,c,ont’d,),Personnel,,What are the staff implications?,,What are the impacts on the overall policy on staff development?,,Image,,How does the product affect the image of the organization?,Software Project Management,17,,SA – Portfolio Management,,suitable for product developed by a
14、software company for an organization,,outsourcing,,need to assess the product for the,client,organization,,Programme management issues apply,,need to carry out strategic assessment for the,servicing,software company,Software Project Management,18,,SA – Portfolio Management Issues,,Long-term goal,of
15、the,software,company,,The,effects of the project on,the portfolio of the company,,An,y,added-value to the overall portfolio of the company,Software Project Management,19,,Technical Assessment,,Functionality against hardware and software,,The,,strategic IS plan of the organization,,any constraint,s,i
16、mposed by the IS plan,Software Project Management,20,,Economic Assessment,,Why?,,Consider whether the project is the best among other options,,Prioritise the projects so that the resources can be allocated effectively if several projects are underway,Software Project Management,21,,Economic Assessme
17、nt (,c,ont’d,),How?,,Cost-benefit analysis,,Cash flow forecasting,,Various cost-benefit evaluation techniques,,NPV and IRR,Software Project Management,22,,EA – Cost-benefit Analysis,,A standard way to assess the economic benefits,,Two steps,,Identify and estimate all the costs and benefits of carryi
18、ng out the project,,Express the costs and benefits in a common unit for easy comparison (e.g. $),Software Project Management,23,,EA – Cost-benefit Analysis (,c,ont’d,),Costs,,Development costs,,Setup costs,,Operational costs,Software Project Management,24,,EA – Cost-benefit Analysis (,c,ont’d,),Bene
19、fit,,Direct benefits,,Assessable indirect benefits,,Intangible,无形的,,benefits,Software Project Management,25,,EA – Cash Flow Forecasting,,What?,,Estimation of the cash flow over time,,Why?,,An excess of estimated benefits over the estimated costs is not sufficient,,Need detailed estimation of benefit
20、s and costs versus time,Software Project Management,26,,EA – Cash Flow Forecasting (Cont’d),,Expenditure,Income,Software Project Management,27,,EA – Cash Flow Forecasting (Cont’d),,Need to forecast,the expenditure and the income,,Accurate forecast is not easy,,Need to revise the forecast from time t
21、o time,Software Project Management,28,,Cost-benefit Evaluation Techniques Example,Year,Project 1,Project 2,Project 3,Project 4,0,-100,000,-1,000,000,-100,000,-120,000,1,10,000,200,000,30,000,30,000,2,10,000,200,000,30,000,30,000,3,20,000,200,000,30,000,30,000,4,20,000,200,000,20,000,25,000,5,100,000
22、,350,000,20,000,50,000,Net Profit,60,000,150,000,30,000,45,000,Payback,5,5,4,4,ROI,12%,4%,10%,11%,Software Project Management,29,,Cost-benefit Evaluation Techniques,,Net profit,,= Total income – Total costs,,Payback period,,= Time taken to break even,,Return on Investment (ROI),Software Project Mana
23、gement,30,,Cost-benefit Evaluation Techniques – NPV,,Net present value (NPV),,It is the sum of the present values of all future amounts.,,Present value,is the value of which a future amount worth at present,,It takes into account the profitability of a project and the timing of the cash flows,Softwa
24、re Project Management,31,,Cost-benefit Evaluation Techniques – NPV (,c,ont’d,),Discount rate,is the annual rate by which we discount future earning,,e.g. If,,discount rate is 10% and the return of an investment in a year is $110, the present value of the investment is $100.,Software Project Manageme
25、nt,32,,Cost-benefit Evaluation Techniques – NPV (cont’d),Let,n,be the number of year and,r,be the discount rate, the present value (PV) is given by,Software Project Management,33,,Cost-benefit Evaluation Techniques – NPV (,c,ont’d,),Issues in NPV,,C,hoos,ing,,an appropriate discount rate,is difficul
26、t,,Ensuring that the rankings of projects are not sensitive to small changes in discount rate,Software Project Management,34,,Cost-benefit Evaluation Techniques – NPV (,c,ont’d,),Guidelines:,,Use the standard rate prescribed by the organization,,Use interest rate + premium,额外费用,,rate,,Use a target r
27、ate of return,,Rank the projects using various discount rates,Software Project Management,35,,Cost-benefit Evaluation Techniques – NPV (,c,ont’d,),Disadvantage,,May not be directly comparable with earnings from other investments or the costs of borrowing capital,Software Project Management,36,,Cost-
28、benefit Evaluation Techniques – IRR,Internal Rate of Return (IRR),,The percentage discount rate that would produce a NPV of zero,,A relative measure,Software Project Management,37,,Cost-benefit Evaluation Techniques – IRR (cont’d),11,9,8,-3000,3000,6000,9000,12,10,Discount rate (%),Net Present Value
29、($),0,Software Project Management,38,,Cost-benefit Evaluation Techniques – IRR (,c,ont’d,),Advantages,,Convenient,,Directly comparable with rate of return on other projects,and with interest rates,,Useful,,Dismiss a project due to its small IRR value,,Indicate further precise evaluation of a project
30、,,Supported by MS Excel and Lotus 1-2-3,Software Project Management,39,,Estimation,Why? – to define the project budget and to ‘refine’ the product to realize the budget,,Who? – the manager,,What? – size and cost,,When? – always,,How? – techniques and models,Software Project Management,40,,Issues rel
31、ated to Estimation,Difficult to make accurate estimation,,Better to have previous data and analyze the actual values against their estimates so that you know how accurate you are,,Even better to have previous data of the whole organization so that you know how accurate the estimation method, if any,
32、 used within the organization is,Software Project Management,41,,Positive Attitude Towards Estimation,Use your estimation as a guide to manage your project,,From time to time, you need to revise your estimation based on the current status of the project,Software Project Management,42,,Estimation App
33、roaches,Expert,judgement,,Ask the knowledgeable experts,,Estimation by analogy,,Use the data of a similar and completed project,,Pricing to win,,Use the price that is low enough to win the contract,Software Project Management,43,,Estimation Approaches (,c,ont’d,),Top-down,,An overall estimate is det
34、ermine,d,and,then,broken down into each component task,,Bottom-up,,The estimates of each component task are aggregate to form the overall estimate,,Algorithmic model,,Estimation is based on the,characteristics of the product and the development environment,.,Software Project Management,44,,Size Esti
35、mation,Problems related to size estimation,,Size Estimation Model,,Function Point Analysis (FPA),Software Project Management,45,,Problems related to size estimation,Nature of software,,Novel,新奇的,application of software,,Fast changing technology,,Lack of homogeneity,同质,of project experience,,Subjecti
36、ve nature of estimation,,Political implication with the organization,Software Project Management,46,,Function Point Analysis (FPA),Developed by A. Albrecht in IBM,,Aim: To estimate the LOC of a system,,,LOC of system,,= FP of system,×,LOC-per-FP of the language,Software Project Management,47,,Functi
37、on Point Analysis (cont’d),Idea: Software system comprises of five major components (or,,external user type,),,External input types,,External output types,,Logical internal file types,,External interface file types,,External inquiry types,Software Project Management,48,,Function Point Analysis,- Ste
38、ps,Identify each instance of each external user type in the proposed system,,Classify each instance,实例,as having high, medium or low complexity,,Assign the FP of each instance,,FP of the system = sum of FP of individual components,Software Project Management,49,,Function Point Analysis,Number of,FPs
39、,Complexity,,,External user type,Low,Average,High,External input type,3,4,6,External output type,4,5,7,Logical internal file type,7,10,15,External interface file type,5,7,10,External inquiry type,3,4,6,Software Project Management,50,,Function Point Analysis,- Example,A component,of an inventory syst
40、em consisting of ‘Add a record’, ‘Delete a record’, ‘Display a record’, ‘Edit a record’, and ‘Print a record’ will have,,3 external input types,,1 external output type,,1 external inquiry type,,Then, assign FPs based on the complexity of each external types,Software Project Management,51,,Function P
41、oint Analysis (cont’d),Other issues,,The assignment of level of complexity is rather subjective,,International FP User Group (IFPUG) imposes rules on assigning the level of complexity to individual external user types,,imposes,sth,.,,on,…,施加,…,于,…,Software Project Management,52,,Object Point Analys
42、is,Similar to function point analysis,,Used on 4GL,第四代语言,,development projects,,Take account of features that may be more readily identifiable if the system is built on a high-level application building tools,Software Project Management,53,,Object Point Analysis – Steps,,Identify the number of scree
43、ns, reports and 3GL,第三代语言,,components,,Classify each object as Simple, Medium and Difficult,,Assign the weight accordingly,,Calculate the total object points,,Total OP = sum of individual OP × weighting,Software Project Management,54,,Object Point Analysis – Steps (,c,ont’d,),Deduct,扣除,,the reused o
44、bjects (r% reused),,NOP = OP × (1 – r%),,Identify the productivity rate of both developer and CASE,,Productivity rate = average of the two,PRs,,Calculate the effort,,Effort = NOP / Productivity Rate,Software Project Management,55,,Object Point Analysis –,,Screens,,Number and source of data tables,,,
45、Number of views contained,Total < 4,,(<2 server, <2 client),Total < 8,,(2-3 server, 3-5 client),Total 8+,,(>3 server, >5 client),< 3,Simple,Simple,Medium,3 – 7,Simple,Medium,Difficult,8+,Medium,Difficult,Difficult,Software Project Management,56,,Object Point Analysis –,,Reports,,Number and source of
46、 data tables,,,Number of sections contained,Total < 4,,(<2 server, <2 client),Total < 8,,(2-3 server, 3-5 client),Total 8+,,(>3 server, >5 client),< 2,Simple,Simple,Medium,2 or 3,Simple,Medium,Difficult,> 3,Medium,Difficult,Difficult,Software Project Management,57,,Object Point Analysis,–,Complexity
47、 Weightings,,Complexity,,,Type of object,Simple,Medium,Difficult,Screen,1,2,3,Report,2,5,8,3GL component,N/A,N/A,10,Software Project Management,58,,Object Point Analysis –,,Productivity Rate,,Very low,Low,Nominal,High,Very High,Developer’s experience and capability,4,7,13,25,50,CASE maturity and cap
48、ability,4,7,13,25,50,Software Project Management,59,,Object Point Analysis – Issues,,Adopted in Boehm’s COCOMO II in the application composition stage,,Software Project Management,60,,Object Point Analysis – Example,,See separate handout,分发的印刷品,Software Project Management,61,,Cost Estimation,Cost Es
49、timation Model,,COCOMO II,Software Project Management,62,,Constructive Cost Model II,(COCOMO II),A parametric cost model,,Important aspects of software project are characterized by variables (or, parameters),,Once the value of the parameters are determined, the cost can be computed from the equation
50、,Software Project Management,63,,C,OCOMO II,(cont’d),Recognize,different approaches to software development,,Prototyping, Incremental development etc.,Software Project Management,64,,A history of COCOMOs,COCOMO,originally proposed by Boehm in 1981, now called,COCOMO,,81,,Later evolved to,Ada,,COCOMO
51、,in 1989,,In 1995, Boehm proposes,COCOMO,,II,Software Project Management,65,,COCOMO II,A family of models,,Use different models in,3,different stages of the project,,3 stages: application composition, early design and post architecture,,Support,,estimation early in the process,,Allow,further detaile
52、d estimation after the system architecture has been defined,Software Project Management,66,,COCOMO II (,c,ont’d,),The basic model equation,,Effort = Constant × (Size),scale factor,,,× Effort Multiplier,,Effort in terms of person-month,,Size: Estimated Size,in KSLOC,,Scale Factor:,a combined effects
53、of factors related to the process,,Effort,Multiplier,(E,M,),:,a combined effect of factors related to the effort,Software Project Management,67,,The,Application Composition Stage,Estimation at the early stage,,Corresponding to exploratory,探索性,,work such as prototyping,,Use object points to estimate
54、the size of the product,Software Project Management,68,,The,E,arly,D,esign,Stage,Estimate,after the requirement,s,specification,is,completed,and,possibly with some design,,Use the basic model equation,,Estimate the size,by,FPs,(preferred) or KSLOC,,Assign process exponent estimation accordingly,Soft
55、ware Project Management,69,,The Early Design Stage –,Scale Factor,Estimation on the,scale,factor,,A combined effect of 5 parameters,,Application,precedentedness,,Process flexibility,,Architecture risk resolution,,Team cohesion,,Process maturity,Software Project Management,70,,The Early Design Stage
56、– Scale Factor (cont’d),Parameter,Very Low,,(0.05),Low,,(0.04),Nominal,,(0.03),High,,(0.02),Very High,,(0.01),Extra High,,(0.00),Precedentedness,Thoroughly unprecedented,Largely unprecedented,Somewhat unprecedented,Generally familiar,Largely familiar,Thoroughly familiar,Development flexibility,Rigor
57、ous,严格的,Occasional relaxation,Some relaxation,General conformity,Some conformity,General goals,Architecture risk resolution,Little,,20%,Some,,40%,Often,,60%,Generally 75%,Mostly,,90%,Full,,100%,Team cohesion,Very difficult interactions,Some difficult interactions,Basically cooperative,Largely cooper
58、ative,Highly,,Cooperative,Seamless interactions,Process maturity,Level 1,Level 2,Level 2+,Level 3,Level 4,Level 5,Software Project Management,71,,The Early Design Stage –,Scale Factor,(Cont’d),Calculate the,scale factor,based on the equation,,Scale factor,= 1.01 + sum of the values,Software Project
59、Management,72,,The Early Design Stage – Effort,Multiplier,7 factors,on Effort Multiplier,,product Reliability and,ComPleXity,(RCPX),,required reusability (RUSE),,Platform,DIFficulty,(PDIF),,PERSonnel,capability (PERS),,PeRsonnel,,EXperience,(PREX),,FaCILities,available (FCIL),,SChEDule,pressure (SCE
60、D),Software Project Management,73,,The Early Design Stage – Effort,Multiplier,(,c,ont’d,),Assess each factor by,,Very low, low, nominal, high,,,very high,, and extra high,,Assign each factor using a value between 0.5 and 1.5 (inclusive,包括的,),,E,M,is the product of all these values,Software Project M
61、anagement,74,,The Early Design Stage – Effort Multiplier (cont’d),Early Design,Very Low – Extra High,RCPX,0.5 – 1.5,RUSE,0.5 – 1.5,PDIF,0.5 – 1.5,PERS,1.5 – 0.5,PREX,1.5 – 0.5,FCIL,1.5 – 0.5,SCED,1.5 – 0.5,Software Project Management,75,,The Early Design Stage,– Example,See separate handout,,Softwar
62、e Project Management,76,,The,P,ost-architecture,Stage,Estimation,after the software architecture has been defined,,The same basic model equation,,Size estimation by KSLOC (preferred) or,FPs,,Same process exponent estimation,,17 factors in E,M,(more than 7 in early design stage),Software Project Mana
63、gement,77,,The,P,ost-architecture,Stage – Effort Multiplier,17 factors in 4 different categories,,Product attributes,,Platform attributes,,Personnel attributes,,Project attributes,Software Project Management,78,,The,P,ost,-architecture,Stage – Effort Multiplier,Product attributes,,Required reliabili
64、ty (RELY)*,,Database size (DATA),,Product complexity (CPLX)*,,Required reuse (RUSE)**,,Documentation (DOCU),,*Relate to RCPX in early design stage,Software Project Management,79,,The,P,ost-architecture,Stage – EAF (Cont’d),Platform attributes,,execution TIME constraint (TIME)*,,main,STORage,constrai
65、nt (STOR)*,,Platform,VOLatility,(PVOL)*,,*Related to Platform,DIFficulty,(PDIF) in early design stage,Software Project Management,80,,The,P,ost-architecture,Stage – EAF (Cont’d),Personnel attributes,,Analyst,CAPabilities,(ACAP)^,,Application,EXPerience,(AEXP)*,,Programmer,CAPabilities,(PCAP)^,,Perso
66、nnel,EXPerience,(PEXP)*,,programming Language/Tool,EXperience,(LTEX)*,,Personnel,CONtinuity,(PCON)^,Software Project Management,81,,The,P,ost-architecture,Stage – EAF (Cont’d),Project attributes,,use of software,TOOLs,(TOOL)*,,multiSITE,development team communications (SITE)*,,*Relate to FCIL in early design model,Software Project Management,82,,EAF Relations,Early Design,Post-Architecture,RCPX,RELY, DATA, CPLX, DOCU,RUSE,RUSE,PDIF,TIME, STOR, PVOL,PERS,ACAP, PCAP, PCON,PREX,AEXP, PEXP, LTEX,FCI
- 温馨提示:
1: 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
2: 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
3.本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
5. 装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。